Wednesday, March 14, 2007
Finally, we can begin!!!
Well, the three weeks took five months with a lot of frustration. Our building engineer is not the fastest man on the planet but he finally got it done.
We have now poured the concrete for the basement slab and had great help from our friends Jack, Mark and Gil, without them it would have been impossible since Stefan was really sick with the flu.
We tried to add some pictures but this blog is not cooperating at this time but as soon as it does we'll put some in.
We have now poured the concrete for the basement slab and had great help from our friends Jack, Mark and Gil, without them it would have been impossible since Stefan was really sick with the flu.
We tried to add some pictures but this blog is not cooperating at this time but as soon as it does we'll put some in.
Monday, November 27, 2006
November 22nd, We have finally received the blue prints!
After almost 3 months we have finally received the calculations from the building engineer. This guy has been stalling and making every excuse in the book of why he didn't make the 2-4 week deadline that he promised us. Stefan met up with him at Riverside County to file the calculations for the building permit and they told him it should take 2-3 weeks before we get the permit.
We are hoping to start building in the beginning of January and we will post more pictures as we progress.
One good thing about this is that Stefan broke his toe this last weekend so he is a little incapacitated and can't do much work anyway...........
We are hoping to start building in the beginning of January and we will post more pictures as we progress.
One good thing about this is that Stefan broke his toe this last weekend so he is a little incapacitated and can't do much work anyway...........
Tuesday, October 10, 2006
Pure Perseverance
Thursday, September 14, 2006
Tuesday, September 12, 2006